CAPITAL IMPROVEMENTS

Through capital projects, the Stamford JCC strives to make enhancements and upgrades to better serve the existing community today and provide a high-quality, welcoming and inclusive environment for the community in the future. With an aim to transform our center; modernizing the facilities, updating and repairing 40 year old infrastructure and committing to space maximization so that we can better serve our community.

 

PROJECTS IN PROGRESS

Multipurpose Classroom Wing
The scope of this project includes converting existing office and meeting space into a new multipurpose classroom wing in the front of the building, and redesign the front entrance to answer security and access control challenges. The project will take approximately 6-9 months.

The multipurpose classroom wing will allow for The JCC Sara Walker Nursery School to move to our Newfield Avenue Campus, as well as, house a new infant childcare room and will serve our KidsPlace, Inclusion, Day Camps@The J and membership communities throughout the year.

This is a project for the community; like the locker room project, the gymnasium and the pool renovations, these are only accomplished by continued philanthropic investments by our community members and generous supporters. Please contact Marshall Kurland, JCC CEO, at mkurland@stamfordjcc.org to get involved in supporting The JCC’s continued transformation.

 

  

   

Week of 6/24/2021 Update

 

  

   

Week of 6/17/2021 Update

 

  

   

Week of 6/10/2021 Update

 

  

   

Week of 6/3/2021 Update

 

  

   

Week of 5/27/2021 Update

 

   

    

Week of 5/20/2021 Update

 

  

  

Week of 5/13/2021 Update

 

  

   

Week of 5/6/2021 Update

 

  

  

Week of 4/29/2021 Update

 

  

   

Week of 4/22/2021 Update

 

  

   

Week of 4/15/2021 Update

 

  

  

Week of 4/8/2021 Update

 

  

   

Week of 4/1/2021 Update

 

  

   

Week of 3/25/2021 Update

 

  

   

Week of 3/18/2021 Update

 

  

   

Week of 3/11/2021 Update

 

  

   

Week of 3/4/2021 Update

 

  

   

Week of 2/28/2021 Update

 

  

   

Week of 2/15/2021 Update

 

   

    

Week of 2/11/2021 Update

 

  

 

Week of 2/4/2021 Update

 

  

   

Week of 1/25/2021 Update

 

  

  

Week of 1/18/2021 Update

 

  

   

Week of 1/11/2021 Update

 

  

  

Week of 1/4/2021 Update

 

  

  

Week of 12/28/2020 Update

 

  

Week of 12/21/2020 Update

 

  

  

Week of 12/14/2020 Update

 

  

  

Proposed

 

  

Before 

 

 

COMPLETED 

Locker Room Renovation - PHASE I
The first phase of the project will be the complete remodel and renovation of the upstairs locker rooms. The new space will serve and accommodate both the general and executive locker room (XLR) members. Once complete, the redesigned space will have new showers, sauna and steam rooms, restrooms, lockers, and will have separate XLR and general member changing and locker spaces.

  

  

Before

 

After

 

 

August Closure Upgrades
New flooring in main corridor, the Board Room and the Conference Room and upgrades to café.

    

Before

 

    

After

 

 

KinderPlace Expansion
New classroom opened for 2018-2019 school year. 

After

 

 

Gymnasium Renovation
New floors with redesigned court lines • New wall pads covering the entirety of the wall space • New lighting • Volleyball net system • Brand new bleachers

  

Before

 

  

After 

 

 

Pool Renovation
New tile for the entire pool deck • Observation deck renovation • New paint for the pool area

  

Before

 

  

After

  

Subscribe to Our Newsletter!

Next Upcoming Event...

3
Aug

Our Community CAN Make a Difference Food Drive

Contactless Drop-Off at the Stamford JCC The Stamford JCC’s JCares will be holding a canned food drive to benefit the Schoke Jewish Family Service and the Freedberg Family Kosher Food Pantry of Fairfield County. The food pantry serves the